Traffic Signal Light Solution (Full Project Lifecycle)

page-721-834

 

Project Initiation & Customer Requirement Collection
  • Receive project inquiry from customer, confirm project location: Ban Mai Mongkol Intersection, Tambon Mae Mo, Lampang, Thailand
  • Collect key requirements: intersection type, traffic flow, power supply, control mode, construction period, acceptance standard
  • Conduct on-site survey: check road conditions, pipeline layout, pole installation position, foundation environment, lightning protection & grounding conditions

 

Demand Analysis & Scheme Planning

 

 

  • Define system configuration: Φ300mm LED traffic signals (red/yellow/green/right-turn green), intelligent signal controller, galvanized steel poles, concrete foundation
  • Confirm structural parameters:

○ Galvanized steel poles: Φ4''(4.5mm thick), Φ5''(5.0mm thick), Φ6''(5.0mm thick)

○ Foundation: 1:3:5 concrete, 30×30cm steel base plate (10mm thick), 6mm stiffeners

○ Grounding: Φ16mm×2.4m copper-clad steel ground rod

○ Wiring: Φ2'' RSC conduit to concrete junction box

  • Control functions: automatic, manual, yellow flash, all red, phase adjustment, directional control
  • Comply with local traffic safety and electrical standards

 

 

Detailed Design & Drawing Output
  • Structural design: pole details, foundation plan, section details, grounding layout
  • Electrical design: controller cabinet wiring, signal driver circuit, power distribution, interface (Ethernet, USB, RS232)
  • Control logic design: phase file, period file, special date file, timing plan
  • Output documents: construction drawings, wiring diagrams, BOM list, technical specification
page-1200-1200

 

Production & Material Procurement

 

Procure raw materials

Galvanized steel pipes, steel plates, LED modules, controller components, wires, grounding rods

01

Fabricate structural parts

Poles, base plates, stiffeners, conduits, junction boxes

02

Assemble electrical parts

Signal light heads, mainboard, LCD touch panel, power distribution module, signal drivers

03

Conduct in-process quality inspection

Dimension, welding, galvanizing, electrical performance

04

 

Factory Testing & Aging

 
01.

Electrical test

Luminance, chromaticity, insulation, voltage withstand, waterproof rating

02.

Function test

Automatic operation, manual control, yellow flash, all red, phase switch, communication

03.

Aging test

Continuous power-on for over 24 hours to ensure stability

04.

Issue factory test report, certificate, and packing list

 

page-800-450

 

Packaging & Delivery
  • Pack products with moisture-proof and shock-proof materials
  • Arrange transportation and track logistics
  • Customer receives goods, checks quantity and appearance, signs receipt

 

On-site Installation & Commissioning
  1. Foundation construction: excavation, reinforcement, concrete pouring, pre-embed conduits and grounding rods
  2. Pole installation: fix poles, connect grounding, fasten base bolts
  3. System assembly: install signal heads, controller cabinet, wiring and waterproof treatment
  4. Commissioning: single-light test → phase debugging → full-automatic operation → function verification
  5. Trial operation: stable running for 3–5 days, record operation log
page-1276-850

 

page-1269-864

 

Customer Acceptance & Project Handover
  • Prepare acceptance documents: as-built drawings, test reports, operation manual, warranty certificate
  • On-site acceptance: check appearance, function, brightness, response, grounding safety
  • Customer confirms qualified and signs acceptance form
  • Provide operation training and after-sales support (warranty, maintenance, remote service)