Traffic Signal Light Solution (Full Project Lifecycle)

- Receive project inquiry from customer, confirm project location: Ban Mai Mongkol Intersection, Tambon Mae Mo, Lampang, Thailand
- Collect key requirements: intersection type, traffic flow, power supply, control mode, construction period, acceptance standard
- Conduct on-site survey: check road conditions, pipeline layout, pole installation position, foundation environment, lightning protection & grounding conditions
Demand Analysis & Scheme Planning
- Define system configuration: Φ300mm LED traffic signals (red/yellow/green/right-turn green), intelligent signal controller, galvanized steel poles, concrete foundation
- Confirm structural parameters:
○ Galvanized steel poles: Φ4''(4.5mm thick), Φ5''(5.0mm thick), Φ6''(5.0mm thick)
○ Foundation: 1:3:5 concrete, 30×30cm steel base plate (10mm thick), 6mm stiffeners
○ Grounding: Φ16mm×2.4m copper-clad steel ground rod
○ Wiring: Φ2'' RSC conduit to concrete junction box
- Control functions: automatic, manual, yellow flash, all red, phase adjustment, directional control
- Comply with local traffic safety and electrical standards
- Structural design: pole details, foundation plan, section details, grounding layout
- Electrical design: controller cabinet wiring, signal driver circuit, power distribution, interface (Ethernet, USB, RS232)
- Control logic design: phase file, period file, special date file, timing plan
- Output documents: construction drawings, wiring diagrams, BOM list, technical specification

Production & Material Procurement
Procure raw materials
Galvanized steel pipes, steel plates, LED modules, controller components, wires, grounding rods
01
Fabricate structural parts
Poles, base plates, stiffeners, conduits, junction boxes
02
Assemble electrical parts
Signal light heads, mainboard, LCD touch panel, power distribution module, signal drivers
03
Conduct in-process quality inspection
Dimension, welding, galvanizing, electrical performance
04
Factory Testing & Aging
Electrical test
Luminance, chromaticity, insulation, voltage withstand, waterproof rating
Function test
Automatic operation, manual control, yellow flash, all red, phase switch, communication
Aging test
Continuous power-on for over 24 hours to ensure stability
Issue factory test report, certificate, and packing list



- Pack products with moisture-proof and shock-proof materials
- Arrange transportation and track logistics
- Customer receives goods, checks quantity and appearance, signs receipt
- Foundation construction: excavation, reinforcement, concrete pouring, pre-embed conduits and grounding rods
- Pole installation: fix poles, connect grounding, fasten base bolts
- System assembly: install signal heads, controller cabinet, wiring and waterproof treatment
- Commissioning: single-light test → phase debugging → full-automatic operation → function verification
- Trial operation: stable running for 3–5 days, record operation log


- Prepare acceptance documents: as-built drawings, test reports, operation manual, warranty certificate
- On-site acceptance: check appearance, function, brightness, response, grounding safety
- Customer confirms qualified and signs acceptance form
- Provide operation training and after-sales support (warranty, maintenance, remote service)